property strategy
Campus Tours
Folkestone
The Folkestone campus has a good location and therefore initial findings suggest development on the existing site rather than moving the college away from the site. Any development would be subject to funding, so a full and thorough appraisal of all options is needed before the College commits.
• A Block refurbishment underway – expected completion Mid August.
• Reception – signage to be improved. Raised with Estates and Business Support staff.
• Survey to be undertaken to review essential maintenance and redecoration works.
• E Block Construction – HNW Architects to review mezzanine floor requirements
• New Build – further work with HNW Architects to assess spatial allocation and requirements – 3800 sq m at present.
• Planning Permission – letter submitted by Planning Consultant to Shepway DC to notify them of intended timescale for new build and permission for land disposal.
• Air conditioning and enhanced lighting works underway in Chapel
• Planned works to car parking barriers – implementation date be advised
• Access controls – review to ensure no operational issues
• Gym – equipment being removed, temporary area being used for student assessments. Refurbishment works underway shortly. Target date for completion is early June.
This page will be updated with new information as and when there is anything to report.